PMP Introduction and Fundamentals – Practice Questions

pmp introduction and fundamentals practice questions - PMP Introduction and Fundamentals - Practice Questions

Q1: Which of the following process groups apply to all projects?
A. Planning, Monitoring and Controlling, Closing
B. Initiating, Planning, Closing
C. Initiating, Planning, Executing, Monitoring and Controlling, Closing
D. Planning, Executing, Closing

Q2: Project Manager alongwith the stakeholders has determined the high level schedule constraints, which process group is the project in?
A. Closing
B. Stakeholder Management
C. Planning
D. Initiating

Q3: One of the major outputs of the initiating process group is?
A. OPA
B. EEF
C. Both A and B
D. Project Charter

Q4: While doing the Validate Scope process, somebody asked the Project Manager which process group was he working in?
A. Planning
B. Monitoring and Controlling
C. Execution
D. Closing

Q5: Which one of the following is the least important stakeholder?
A. Project Team Members working on the project
B. Competitor whose organization will be affected by the new product release
C. Project Manager
D. Customer who will be using the end product or service

Q6: Which of the following isn’t a characteristic of a Project?
A. Temporary
B. Contains activities that are inter-related
C. Repeats every month
D. Has a definite beginning and end

Q7: Your organization is a Projectized Organization, who does the Project Team reports to?
A. Functional Manager
B. Project Manager
C. Both A and B
D. None of the above

Check all the articles on Project Management Basics

ANSWERS

Q1: C. Initiating, Planning, Executing, Monitoring and Controlling, Closing
Q2: D. Initiating
Q3: D. Project Charter
Q4: B. Monitoring and Controlling
Q5: B. Competitor whose organization will be affected by the new product release
Q6: C. Repeats every month
Q7: B. Project Manager

Check out other topics for PMP Practice

More PMP Practice Questions,

ir?t=soyaison 21&l=alb&o=31&a=1628254610 - PMP Introduction and Fundamentals - Practice Questionsir?t=soyaison 21&l=alb&o=31&a=1986067416 - PMP Introduction and Fundamentals - Practice Questionsir?t=soyaison 21&l=alb&o=31&a=1719192316 - PMP Introduction and Fundamentals - Practice Questions

Products from Amazon.in

    2 Comments on “PMP Introduction and Fundamentals – Practice Questions”

    1. Q3: One of the major outputs of the initiating process group is?
      A. OPA
      B. EEF
      C. Both A and B
      D. Project Charter

      Ans: D. Project Charter
      Is this correct answer? .. Input is project charter and not Output i think

      1. Project Charter is indeed an output of the Initiating process group. Develop Project Charter is one of the only two processes in Initiating process group

    Leave a Reply

    Your email address will not be published. Required fields are marked *