Cost Management

All PMP Cost Management Formulas (Earned Value Management – CPI, SPI, CV, SV, EAC, ETC, TCPI, VAC)

Schedule Performance Index

SPI = EV/PV
EV = Earned Value
PV = Planned Value

< 1 behind schedule
= 1 on schedule
> 1 ahead of schedule

Cost Performance Index

CPI = EV/AC
EV = Earned Value
AC = Actual Cost

< 1 Over budget
= 1 On budget
> 1 Under budget

Schedule Variance

SV = EV-PV
EV = Earned Value
PV = Planned Value

< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule

Cost Variance

CV = EV-AC
EV = Earned Value
AC = Actual Cost

< 0 Over budget
= 0 On budget
> 0 Within budget

Estimate At Completion, if original is flawed

EAC = AC+ETC
AC = Actual Cost
ETC = Estimate to Completion

if the original estimate is based on wrong data/assumptions or circumstances have changed ETC mentioned here is a ‘new ETC’

Estimate At Completion, if BAC remains the same

EAC = AC+BAC-EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value

the variance is caused by a onetime event and is not likely to happen again

Estimate At Completion, if CPI remains the same

EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index

if the CPI would remain the same till end of project, i.e. the original estimation is not accurate

Estimate At Completion, if substandard performance continues

EAC = AC+(BAC-EV)/(CPI*SPI)
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index

use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used

To Complete Performance Index (TCPI)

TCPI = (BAC-EV)/ (BAC-AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost

TCPI is basically – Remaining Work / Remaining Funds

< 1 Under budget
= 1 On budget
< 1 Over budget

If EAC is available use EAC-AC instead of BAC-AC

Estimate To Complete (ETC)

ETC = EAC-AC
EAC = Estimate at Completion
AC = Actual Cost

Variance At Completion (VAC)

VAC = BAC-EAC
BAC = Budget at completion
EAC = Estimate at Completion

Inference

For variances like SV, CV and VAC – negative is bad, positive is good

For indices like CPI and SPI – less than 1 is bad, more than 1 is good. However, the opposite is true for TCPI

Diagrammatic Representation

Check more articles on Cost Management

Shoaib Qureshi

Passionate Project Manager. Managing projects with precision since 2011. Helping Project Managers Get Certified and Stay Ahead - powered by PMC Lounge.

Recent Posts

Why PMP Needs 3 Years Exp, PM Jobs in AI Era, PMP Mindset, PMBOK Reviewers: PMC Q&A

https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…

16 hours ago

Everything you need to know about PMI-ACP in 2026

https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…

4 days ago

5 Issues with the 5-Why Technique Nobody Talks About

https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…

7 days ago

Everything you need to know about CAPM in 2026

https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…

1 week ago

The Dangers of Switching Industries with PMP (that nobody told you about!)

https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…

2 weeks ago

CSM vs PSM – The Undisputed Scrum Champion

https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…

2 weeks ago