SPI = EV/PV
EV = Earned Value
PV = Planned Value
< 1 behind schedule
= 1 on schedule
> 1 ahead of schedule
CPI = EV/AC
EV = Earned Value
AC = Actual Cost
< 1 Over budget
= 1 On budget
> 1 Under budget
SV = EV-PV
EV = Earned Value
PV = Planned Value
< 0 Behind schedule
= 0 On schedule
> 0 Ahead of schedule
CV = EV-AC
EV = Earned Value
AC = Actual Cost
< 0 Over budget
= 0 On budget
> 0 Within budget
EAC = AC+ETC
AC = Actual Cost
ETC = Estimate to Completion
if the original estimate is based on wrong data/assumptions or circumstances have changed ETC mentioned here is a ‘new ETC’
EAC = AC+BAC-EV
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
the variance is caused by a onetime event and is not likely to happen again
EAC = BAC/CPI
BAC = Budget at completion
CPI = Cost performance index
if the CPI would remain the same till end of project, i.e. the original estimation is not accurate
EAC = AC+(BAC-EV)/(CPI*SPI)
AC = Actual Cost
BAC = Budget at completion
EV = Earned Value
CPI = Cost Performance Index
SPI = Schedule Performance Index
use when the question gives all the values (AC, BAC, EV, CPI and SPI), otherwise, this formula is not likely to be used
TCPI = (BAC-EV)/ (BAC-AC)
BAC = Budget at completion
EV = Earned value
AC = Actual Cost
TCPI is basically – Remaining Work / Remaining Funds
< 1 Under budget
= 1 On budget
< 1 Over budget
If EAC is available use EAC-AC instead of BAC-AC
ETC = EAC-AC
EAC = Estimate at Completion
AC = Actual Cost
VAC = BAC-EAC
BAC = Budget at completion
EAC = Estimate at Completion
For variances like SV, CV and VAC – negative is bad, positive is good
For indices like CPI and SPI – less than 1 is bad, more than 1 is good. However, the opposite is true for TCPI
Check more articles on Cost Management
https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…
https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…
https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…
https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…
https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…
https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…