What is Critical Path? How to find it?

Critical Path Method or, as it is endearingly known, CPM is the most important tool to keep your projects on track. Do you remember Network Diagrams? Every network diagram has a Critical Path.

Critical Path

Critical Path is basically the longest string of activities in the network diagram. So if you add durations of all the activities on all the paths in your network diagram, the one with the highest duration is the Critical Path.

The most important aspect of critical path is the fact that a delay in any of the activities on the critical path is going to delay the entire project. Read the previous line again. Isn’t it obvious that knowing your project’s critical path is, well, quite critical!

This also means that activities not on the critical path can get delayed without impacting the project. This definitely gives you a fair idea of what’s urgent and what can wait. Conversely, this also gives you a fair idea of what activities must finish early for the entire project to complete ahead of schedule.

How to find the Critical Path?

Now it is quite obvious that on real world projects you would be using a software like Microsoft Project to find out the critical path but the software uses the same calculation that we are going to learn here.

Do refer to the video for step-by-step calculation of the critical path in the example below,

Clearly, ACFG is the critical path with the highest duration of 13.

Check more articles on Schedule Management

Shoaib Qureshi

Passionate Project Manager. Managing projects with precision since 2011. Helping Project Managers Get Certified and Stay Ahead - powered by PMC Lounge.

Recent Posts

Why PMP Needs 3 Years Exp, PM Jobs in AI Era, PMP Mindset, PMBOK Reviewers: PMC Q&A

https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…

16 hours ago

Everything you need to know about PMI-ACP in 2026

https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…

3 days ago

5 Issues with the 5-Why Technique Nobody Talks About

https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…

7 days ago

Everything you need to know about CAPM in 2026

https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…

1 week ago

The Dangers of Switching Industries with PMP (that nobody told you about!)

https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…

2 weeks ago

CSM vs PSM – The Undisputed Scrum Champion

https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…

2 weeks ago