Q1: If EV is $550, AC is $650 and PV is $600, what would be the CV?
A. 50
B. -50
C. 100
D. -100
Q2: Which of the following is not a Tool and Technique for the process of Determine Budget?
A. Cost Aggregation
B. Resource Calendars
C. Funding Limit Reconciliation
D. Reserve Analysis
Q3: You are the Project Manager and in the process of midway review at the end of the first year of a $50,000 project. The earned value analysis shows that the PV is $25,000, the EV is $20,000 and the AC is $15,000. What can be determined from these figures?
A. The project is behind schedule and over budget
B. The project is ahead of schedule and under budget
C. The project is ahead of schedule and over budget
D. The project is behind schedule and under budget
Q4: The CPI of 0.73 means?
A. The project would cost 73% more than originally planned
B. The project would cost 27% more than originally planned
C. The project would cost 73% less than originally planned
D. The project is only getting $0.73 out of every $1 spent
Q5: The SPI of 0.67 means?
A. You are ahead of schedule by 33%
B. You are behind schedule by 67%
C. You are progressing at only 67% of the rate originally planned
D. You are progressing at only 33% of the rate originally planned
Check all the articles on Cost Management
Q1: D. -100
Q2: B. Resource Calendars
Q3: D. The project is behind schedule and under budget
Q4: D. The project is only getting $0.73 out of every $1 spent
Q5: C. You are progressing at only 67% of the rate originally planned
Check out other topics for PMP Practice
Most up-to-date PMP Prep Books
https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…
https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…
https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…
https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…
https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…
https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…