Q1: As a Project Manager, under what process group do you work on defining the project scope?
A. Integration Management
B. Planning
C. Initiating
D. Scope Management
Q2: When decomposing the work in the Work Breakdown Structure (WBS), which of the following is NOT true?
A. Decompose until the WBS element cannot be logically decomposed further
B. Decompose until the WBS element can be estimated accurately
C. Decompose until the WBS element can be accomplished by a single project team member
D. Decompose until the WBS element has a meaningful conclusion
Q3: After a significant amount of time and effort dedicated to the creation of the Work Breakdown Structure, it is finally ready. Now you have distributed the WBS to all the relevant stakeholders. You receive an email from John complaining that the WBS isn’t detailed enough. For detailed descriptions of each WBS element, where should John look,
A. Scope Statement
B. WBS Dictionary
C. Stakeholder Register
D. Project Charter
Q4: While working as the Project Manager of a highway construction project, you are visited by the Project Sponsor. The Sponsor asks you to lay 12” thick asphalt and not the 9” which has been mentioned in the scope statement and WBS. What should be your next step?
A. Ask the team to accommodate the request as soon as possible
B. Look for cheaper suppliers so that the cost impact can be minimized
C. Set up an emergency team meeting
D. Refuse the request and ask the sponsor to use the change management system
Q5: The goal of the validate scope process is,
A. To gain formal acceptance of the project deliverables from the sponsor and stakeholders
B. To get everyone in the project working together towards a common goal
C. To inspect scope management documents for defects
D. To verify all the processes in the PMBOK guide are being complied with
Check all the articles on Scope Management
Q1: B. Planning
Q2: C. Decompose until the WBS element can be accomplished by a single project team member
Q3: B. WBS Dictionary
Q4: D. Refuse the request and ask the sponsor to use the change management system
Q5: A. To gain formal acceptance of the project deliverables from the sponsor and stakeholders
Check out other topics for PMP Practice
Most up-to-date PMP Prep Books
https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…
https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…
https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…
https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…
https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…
https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…