Work Performance: Data, Information and Report

During your PMP studies, you are bound to come across three similar sounding terms,

1. Work Performance Data
2. Work Performance Information
3. Work Performance Report

Obviously these are not synonymous terms and a clear understanding of their difference is a must have. Let’s try to solve this puzzle.

Work Performance Data

This is just the initial measurement of the project work being done during the Executing process group. In simpler terms, Work Performance Data can quantify the project work being done during Executing

Work Performance Information

Now that we already have the Work Performance Data, it can be analyzed for conformance with the Project Management Plan. This analysis results in Work Performance Information. Notice how we are ‘analyzing’ here? This is a hint enough to figure out that Work Performance Information is a product of Monitoring and Controlling process group

Work Performance Report

So we had the Data which was analyzed to arrive at Information but how can this be presented to stakeholders? That is where Work Performance Report comes in. Work Performance Report is basically the output of Monitoring and Controlling process group and more specifically the Monitor and Control Project Work process. It is important to note that the information needs of different stakeholders will be different and thus multiple Work Performance Reports may have to be generated

Bottomline is that the Data leads to Information which is then placed in Reports. Do not mix these terms up and your PMP studies will be easier

Check more articles on Integration Management

Shoaib Qureshi

Passionate Project Manager. Managing projects with precision since 2011. Helping Project Managers Get Certified and Stay Ahead - powered by PMC Lounge.

View Comments

  • Your statement on Work Performance Report : - Work Performance Report is basically the output of Monitoring and Controlling process group and more specifically the Monitor and Control Project Work process. .
    Which is (Work Performance Report) NOT aligned with PMBok 6th Edition on page 453 . 11.7 Monitor Risks - The Output is Work Performance Information and is NOT Work Performance Report, pls clarify very confusing

    • Why are you checking Monitor Risks? The article says Monitor and Control Project Work process. Work Performance Report is indeed an output of the Monitor and Control Project Work process

  • Hello to you,

    When we talk about Work Performance reporting, does that mean it is carried out only during Monitor and Controlling Project Work process , which belongs to Monitoring and Control Process Group

    Can you elaborate a bit more please.

Recent Posts

Why PMP Needs 3 Years Exp, PM Jobs in AI Era, PMP Mindset, PMBOK Reviewers: PMC Q&A

https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…

14 hours ago

Everything you need to know about PMI-ACP in 2026

https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…

3 days ago

5 Issues with the 5-Why Technique Nobody Talks About

https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…

7 days ago

Everything you need to know about CAPM in 2026

https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…

1 week ago

The Dangers of Switching Industries with PMP (that nobody told you about!)

https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…

2 weeks ago

CSM vs PSM – The Undisputed Scrum Champion

https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…

2 weeks ago