Q1: Decision tree analysis is a type of
A. Risk Response strategy
B. A subset of EVM Technique
C. A subset of EMV Technique
D. A quantitative risk analysis and modeling technique
Q2: You are purchasing insurance for your project equipment considering how this is a long term project. What type of risk response is this?
A. Acceptance
B. Mitigation
C. Transfer
D. Avoidance
Q3: As a Project Manager, what is the first action you would take as soon as you realize that an unidentified risk has materialized
A. Rework on the risk register to better uncover other such unknown risks
B. Create a work around
C. Inform the senior management about this
D. Inform the customer about possible consequences
Q4: You have used a risk analysis tool that models your project risks by running simulations that calculate random outcomes and probabilities. What is this tool called?
A. EMV Analysis
B. Monte Carlo Analysis
C. Delphi Technique
D. Brainstorming
Q5: How should you not respond to a positive risk or opportunity?
A. Transfer
B. Exploit
C. Share
D. Enhance
Check all the articles on Risk Management
Q1: D. A quantitative risk analysis and modeling technique
Q2: C. Transfer
Q3: B. Create a work around
Q4: B. Monte Carlo Analysis
Q5: A. Transfer
Check out other topics forĀ PMP Practice
Most up-to-dateĀ PMP Prep Books
https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…
https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…
https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…
https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…
https://youtu.be/d1xC3uXtx2Q Guest - Jessie Haraszkiewicz Is project management really that different from raising a child?…
https://www.youtube.com/watch?v=RGqg7yo0rHo The credential is your starting line, not your finish line. While the Google Project…