PMP Practice Questions

Schedule Management – Practice Questions

Q1: You are the Project Manager on a construction project. You have worked with your team to define the dependencies and estimated their durations and resource requirements. Now you are creating the project schedule. Which of the following tools and techniques is of no use at this time?
A. Resource leveling
B. Schedule Compression
C. Critical Chain Method
D. Reserve Analysis

Q2: The customer is looking for the project to be complete 10 days earlier than planned due to marketing constraints. You work with your project team and figure out that this can be achieved if a couple of activities can overlap. This approach is known as?
A. Fast Tracking
B. Crashing
C. Resource Leveling
D. Concurrent Engineering

Q3: Your project team is working on the network diagram to calculate the float. Which of the following is the formula they should be using,
A. Late Finish – Late Start or Early Finish – Early Start
B. Late Start – Late Finish
C. Early Start – Early Finish
D. Late Finish – Early Finish or Late Start – Early Start

Q4: You are the Project Manager of a flyover construction project. While planning you realized that you would need approval from Indian Railways for construction on a certain part of land owned by the railways. These kind of dependencies that originate outside the project are known as?
A. Mandatory Dependency
B. Internal Dependency
C. Discretionary Dependency
D. External Dependency

Q5: You are the project manager for a software project. You have worked with the team to create the project schedule, perform critical path analysis and calculated the values of Early and Late Start, Early and Late Finish as well as Float. Which activities in the project cannot slip without making the project late?
A. Activities with biggest difference between ES and LF
B. The activity with most lag
C. All the activities on the critical path
D. Every activity that slips delays the project

Check all the articles on Schedule Management

Answers

Q1: D. Reserve Analysis
Q2: A. Fast Tracking
Q3: D. Late Finish – Early Finish or Late Start – Early Start
Q4: D. External Dependency
Q5: C. All the activities on the critical path

Check out other topics for PMP Practice

Most up-to-date PMP Prep Books

Shoaib Qureshi

Passionate Project Manager. Managing projects with precision since 2011. Helping Project Managers Get Certified and Stay Ahead - powered by PMC Lounge.

Recent Posts

Why PMP Needs 3 Years Exp, PM Jobs in AI Era, PMP Mindset, PMBOK Reviewers: PMC Q&A

https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…

13 hours ago

Everything you need to know about PMI-ACP in 2026

https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…

3 days ago

5 Issues with the 5-Why Technique Nobody Talks About

https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…

7 days ago

Everything you need to know about CAPM in 2026

https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…

1 week ago

The Dangers of Switching Industries with PMP (that nobody told you about!)

https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…

2 weeks ago

CSM vs PSM – The Undisputed Scrum Champion

https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…

2 weeks ago