Scope Management

Create WBS and Work Breakdown Structure (WBS)

Once you are done with the Define Scope process, the next process in your journey of Scope Management knowledge area is the Create WBS process. WBS stands for Work Breakdown Structure. Below is the PG-KA mapping,

Create WBS is often described as the most important process in Scope Management knowledge area. The reason for that is simple, this is where you create the Work Breakdown Structure or the WBS which is the main output of the entire Scope Management knowledge area.

The formal definition of Create WBS process is,

The process of subdividing project deliverables and project work into smaller, more manageable components. This process provides a framework of what has to be delivered.

WBS is the most important output of this process that completes the Scope Baseline. You might recall the equation from Basics of Scope Management below,

Scope Baseline = Project Scope Statement + Work Breakdown Structure + WBS Dictionary

Let’s look at other inputs, tools and techniques and outputs of this process,

Inputs

Tools and Techniques

Outputs

  • Scope Baseline (remember the equation – Scope Baseline = Project Scope Statement + Work Breakdown Structure + WBS Dictionary)
  • Project Documents Updates

Work Breakdown Structure

Now that we understand the Create WBS process, let’s talk about the Work Breakdown Structure itself.

If you are a newbie in Project Management, one of the many weird terms, you need to get yourself acquainted to, is the WBS. Every single thing that anyone on the project team, including you as the project manager, needs to do is documented in the WBS. The ‘work’ in Work Breakdown Structure refers to work products or deliverables that are the result of activity and not to the activity itself. Thus, WBS isn’t a document that merely lists all the project activities.

Actually, breaking up the definition of WBS into two parts can help comprehend it much better,

  • WBS is ‘deliverable’ oriented (not ‘activity’ oriented)
  • WBS is a hierarchical decomposition of the work

So WBS is basically a way to organize the project team’s work into manageable parts.

An example of a WBS is below,

Check more articles on Scope Management

Shoaib Qureshi

Passionate Project Manager. Managing projects with precision since 2011. Helping Project Managers Get Certified and Stay Ahead - powered by PMC Lounge.

Recent Posts

Why PMP Needs 3 Years Exp, PM Jobs in AI Era, PMP Mindset, PMBOK Reviewers: PMC Q&A

https://youtu.be/7-YSZc9YTEY The PMP exam has one requirement that stops many professionals in their tracks: three…

12 hours ago

Everything you need to know about PMI-ACP in 2026

https://www.youtube.com/watch?v=b9IOF8h8CP0 Your path to leadership in the agile world requires more than just a passing…

3 days ago

5 Issues with the 5-Why Technique Nobody Talks About

https://youtube.com/live/8NUZ0j2XyJI The 5-Why technique is often presented as a perfect tool for root cause analysis.…

7 days ago

Everything you need to know about CAPM in 2026

https://youtu.be/qHwsX9TbAGg?si=RWuHNbFRPnE1U9UE The CAPM is one of the most practical entry points into a project management…

1 week ago

The Dangers of Switching Industries with PMP (that nobody told you about!)

https://youtu.be/njvcYdtPoBU Is the PMP a "golden ticket" to any industry you choose? Many project managers…

2 weeks ago

CSM vs PSM – The Undisputed Scrum Champion

https://youtu.be/nO5FvMggbH4 Choosing between the Certified Scrum Master (CSM) and the Professional Scrum Master (PSM) is…

2 weeks ago