Agile Practice Questions – Part 4
Q1: You are a developer working on a team that is building an app. When you try to commit code for a feature you’ve been working on, your commit doesn’t go …
Agile Practice Questions – Part 4 Read MorePMC Lounge helps Project Managers Get Certified and Stay Ahead
Q1: You are a developer working on a team that is building an app. When you try to commit code for a feature you’ve been working on, your commit doesn’t go …
Agile Practice Questions – Part 4 Read More
Q1: With the help of Scrum Planning tools, the scrum teams take project decisions…A. At the last responsible momentB. CollectivelyC. Just in time (JIT)D. As soon as possible Q2: You …
Agile Practice Questions – Part 3 Read More
Some questions in the PMP exam are tricky. There is definitely some play with words involved. In this video we look at one such ‘Double Negative’ PMP question RELATED LINKS …
Answering tricky PMP questions Read More
Q1: What is the primary objective of negotiation?A. Define the exact responsibilities of each partyB. Clarify the contract scopeC. Get the best deal possibleD. Find a win-win proposition for both …
Procurement Management – Practice Questions Read More
Q1: If EV is $550, AC is $650 and PV is $600, what would be the CV?A. 50B. -50C. 100D. -100 Q2: Which of the following is not a Tool …
Cost Management – Practice Questions Read More
Q1: As a Project Manager, under what process group do you work on defining the project scope?A. Integration ManagementB. PlanningC. InitiatingD. Scope Management Q2: When decomposing the work in the …
Scope Management – Practice Questions Read More