Q1: The Project Manager of a complex IT project is having a one-on-one discussion with a new engineer. The PM explains one of the algorithms that is being developed and asks the Engineer if he would be able to document the functioning of the algorithm and send it to the stakeholders? The Engineer agrees and shares the document. However after going over the document, the PM realizes that the Engineer didn’t really understand the algorithm. Who is at fault for the loss of time and effort?
A. Functional Manager, he shouldn’t have assigned a new engineer on this complex project
B. Project Manager, he should’ve helped create and review the document with the engineer
C. Engineer, he should’ve immediately asked his doubts on the understanding of the algorithm
D. Project Manager, it is his responsibility that the message is clearly understood and get a confirmation from the engineer
Q2: You are managing an Infrastructure project. You have an issue with a team member’s performance. How will you communicate this issue with the team member?
A. Formal Verbal
B. Informal Verbal
C. Formal Written
D. Informal Written
Q3: Your project involves vendors. One of the vendors is requesting confidential information about your project without which they won’t be able to make progress. The vendor would like to know who has the authority to release that confidential information. Which project document should he refer to?
A. Project Charter
B. Scope Management Plan
C. Communications Management Plan
D. Stakeholder Management Plan
Q4: Which of the following is the biggest concern of the virtual team?
A. Different time zones
B. Noise
C. Cultural differences
D. Communications Management
Q5: You are managing a project with 25 team members and one team lead at 3 different locations each. You also have 3 members supporting as part-time project staff. How many communication channels are possible in your project?
A. 496
B. 992
C. 424
D. 32
Check all the articles on Communications Management
ANSWERS
Q1: D. Project Manager, it is his responsibility that the message is clearly understood and get a confirmation from the engineer
Q2: B. Informal Verbal
Q3: C. Communications Management Plan
Q4: B. Noise
Q5: A. 496
Check out other topics for PMP Practice
Most up-to-date PMP Prep Books
I would like to know why was the answer for the fourth question Q4: B. Noise, what we usually struggle with in virtual team meetings is the ability to find a good time for everyone as teams are in different time zones. however, the noise can be managed by setting everyone on mute (video, audio) and one can be allowed to talk (eg: host) and questions can be posted using chat box.
Hi, I cannot find the corrcet answer for the below question, please advice
You are managing a project with 25 team members and one team lead at 3 different locations each. You also have 3 members supporting as part-time project staff. How many communication channels are possible in your project?
the formula is n(n-1)/2. So let’s find out n
In the first line of the question it says you are managing which means project manager is also involved in the communication that is one person. so we sill count him as 1
Next, Project manager is managing 25 members so in total so far we have 1+25
Next, one team lead at 3 locations, total 1+25+3
Next, 3 members as part time also a part of the communication channel
Total 1+25+3+3=32
32(32-1)/2 = 496
You count as 1
25 team members 1 + 25
3 Leaders at each Location 1+25+3
3 Additional members Part Time 1+25+3 + 3 = 32
32 ( 32-1) / 2
32X31/2 = 496
👏👏